![]() |
YELLOW SHEET Office of the State Auditor of Missouri |
August 6, 2003
Report No. 2003-79
Due
to much public attention and the numerous calls and complaints received from
The
The
The April 2003 bond schedule
calculations used lower operating costs and inflation rates than provided for
in the county's project documentation.
The
The Justice Center Fund has
had a negative cash balance since its inception and by the end of May 2003, the
cash balance in this fund was ($267,307).
Monies from other county funds are being borrowed to cover the costs of
the justice center project until other financing is secured.
The January 2003 project
budget reflects a total project cost of approximately $7.1 million, whereas the
April 2003 project budget reflects a total project cost of approximately $7.6
million. The April 2003 bond issue
information indicates the project funds available from the bond issue proceeds
is approximately $7.7 million (proceeds less other fund deposits and
underwriter discounts). A comparison of
these amounts shows that the anticipated project cost is very close
to estimated funds available
for the project from the bond proceeds.
Should bond issue proceeds not be sufficient to cover the total project
costs, other county funds will need to be used.
Given the county's overall poor financial condition, this may not even
be a potential option.
The
In May 2002, the
county contracted with a professional engineer to provide consulting
services for the justice center project.
The contract provides for the consultant to serve as the owner’s
representative and provide consultation and advice in connection with the
justice center project.
The
The county entered into this contract without adequately
evaluating the potential time and cost involved and did not ensure it
documented clear expectations of the owner's representative. The contract did not provide for a maximum
amount. According to the initial project
budget dated June 2002, the owner’s representative fee was estimated at
$100,000. However, this was doubled five
months later to $200,000 on the January 2003 project budget.
The owner’s representative's billings did not include adequate
supporting documentation for services rendered, mileage incurred, and
reimbursable expenses.
Problems
were also noted with other professional services arrangements. Competitive proposals were not always
solicited and documentation regarding the selection process was not
adequate. Some contracts were
either incomplete or not on file at the county.
Project information
provided in the